Installation and production of balcony glass are two separate things. The production of balcony glass includes measuring, drawing, ordering glass, cutting balcony glass profiles, assembling fittings and the last step of gluing the glass.
What reduces or increases the production time is the stage of ordering and delivering the tempered glass from the factory. In different provinces, depending on the conditions of the factories, glass delivery is from 3 to 15 working days.
Installation does not have these steps anymore. The balcony glass installation procedure is a specific and consecutive procedure. Depending on whether the balcony glass work is made of iron or stone, the installation time will increase or decrease.
The process of installing the balcony glass starts from screwing the rails and continues by placing the glass in the rail and then ends with special settings and Regalage.
Recently, in Iran, it is observed that colleagues glue the glass in the project site to speed up the installation of balcony glass, which has its own disadvantages. Write here...